Home › Tender process › Tenders
TendersStatus, phases and AI assistants
← All tendersDEMO-NET-0388 · Etimad · GTPL 2019
Sewer network rehabilitation, 140 km, 3 districts
Buyer: Municipal infrastructure agencyBidder: CWCValue: SAR 185MCloses: 03 Dec (21 days)Bid manager: Bid manager BERP: fusionhigh
Phase 2 of 7 · agent: Tender analyst
Signs: Bid manager, with technical, commercial and legal ownersAnalyse
Requirements, evaluation criteria, deadlines and risks, linked to the source documents.
Gate status: pending
People approve the agent’s output; each requirement is validated by its owner.
Requirement matrix · coordinated by the bid manager
96/204
5 clauses beyond CWC red lines · requirements linked to their source; technical, commercial and legal owners validate their own lines.
Supplier RFQs · Oracle Procurement
Fusion SourcingRFQs are created in Oracle once management approves the bid (phase 4).
Compliance Desk · the reviewer flags and cites, the owners decide
Law applied: GTPL 2019Compliance and evidence pack
Eligibility
1 met
Tender instructions
no items yet
Bid bond
no items yet
Addenda & Q&A
1 gap
Local content
no items yet
Contract terms
1 deviation
Company documents vs closing date (03 Dec) and bid validity
Commercial registration (CR)valid · 2027-03-14
Zakat & VAT certificatevalid · 2027-04-30
GOSI certificateexpires in bid validity · 2026-12-05
Chamber of Commerce membershipexpires before closing · 2026-11-13
Contractor classification (water, grade 1)valid · 2028-01-20
Saudisation (Nitaqat) certificateexpires in bid validity · 2026-12-30
Local content certificate (LCGPA)expires in bid validity · 2027-02-11
Evidence pack · “met” requires a source in the tender and in the bid
| Requirement | Asked in | Answered in | Status | Approved by | Legal action |
|---|---|---|---|---|---|
| Unlimited liability for third-party damage Contract terms · bid v1 | GCC 31 | — | Deviation | — | |
| Addendum 1: scope +12 km in district CAdd. 1 Addenda & Q&A · bid v1 | Add. 1 | — | Missing | — | |
| Contractor classification, networks Eligibility · bid v1 | ITB 4.1 | Vol. 1, p. 9 | Met | Legal reviewer, 8 Nov |
2 items still open before sign-off. Each new addendum re-runs the checks and only the changes come back to Legal.